Fired Heater Risk Ranking – Owners Can Mitigate Risks Of Operation

Fired Heater Risk Ranking – Owners Can Mitigate Risks Of Operation

fired-heater-cover.jpg

…by Eileen Chant and Abby King

Fired heaters are critical equipment items in the process industries and are often overlooked since they don’t fit nicely into a single category of equipment or existing programs in the same way a pump or pressure vessel does. Safe and reliable operation is essential to avoiding adverse health, safety, and environmental consequences. Poor heater conditions and plant practices can increase the risk of a loss of containment (LOC) event, potentially resulting in fire and/or explosion. This can also increase the likelihood of plant personnel being exposed to hazardous situations when starting and operating the heater, or when responding to emergencies. Plants should look for opportunities for improved operations, inspections and maintenance to mitigate the risks associated with the operation of fired heaters.

The risk-based approach described is used to identify potential threats to health and safety during operation by assigning a risk to each identified credible failure. The fired heater risk ranking work process is executed by a team composed of fire-side, operations, process, risk and metallurgical specialists (See Table 1), with typically more than 20 years of experience with an owner company. The outcome of the process includes actionable findings which can be prioritized to effectively mitigate the higher risk levels identified. The actionable findings are specific to the higher risks and include the development and refinement of preventative maintenance, inspection programs, operator surveillance, remaining life assessments, metallurgical upgrades, and implementation or improvement of training programs.

Table 1. Cross Functional Specialist Team for Fired Heater Risk Ranking Execution

Risk-Based Facilitator

 Process Engineer 

 Fired Heater Equipment Specialist 

Metallurgist

Fired Heater Operations

Risk levels are determined by combining the severity (consequence) and probability of potential failures (Risk = Probability x Consequence). The process is semi-quantitative and semi-qualitative, in that probability and consequences are order-of-magnitude estimates driven by the knowledge and experience of the cross functional team, but those estimates are based on calculations incorporated into the software, BechtFiredHeater. The process is dependent on rating the administrative, design and operation practices using a series of critical factors. Once the critical factor rankings are rated by the cross-functional team, BechtFiredHeater computes the probabilities and consequences, and subsequently the risk associated with each credible failure scenario. In addition to Mechanical Integrity, the effect of the controls systems and operator practices are part of the risk ranking algorithm.

Multi-Discipline Specialist Review and Site Visit

The Cross Functional Team kicks off the process by providing the client with a list of data needs, including heater tube-side and fire-side design, operations practices, control systems, and historical data. The data review is followed by a site visit. The specialists conduct a field walkdown of each heater and interviews plant personnel who are responsible for operation of the heater (See Table 2). Templates are used for the interviews to ensure quality and consistency of the process for all heaters. Although it is not always practical, the site visit adds the most value if conducted while the heater is in operation.  Any initial gaps identified are communicated to the site.

Table 2. Specialist Review Areas

Review of heater design

Review and evaluation of previous inspection information

Review of historical and current operating conditions

MOCs documenting changes to the equipment

Review of incident reports (i.e. trips and unplanned outages)

Review of operating procedures and practices

 Interviews with key site personnel (Operations, Process Engineering, Inspection, Reliability, Process Safety Management) 

Field walkdown of each heater


Risk Ranking

The risk ranking process begins with a ranking of Administrative factors for each site. Table 3 shows an example ranking. The rankings are determined via consideration of the programs in effect and quality of implementation for each category. Team discussions leading to consensus are used determine the ranking. For example, the operator surveillance category considers programs for heater monitoring by the operators at the site, such as IR scans, and burner and pilot flame patterns inspection, and consider how well those actions are implemented. Specialist findings with respect to each administrative factor are entered into the software as descriptive text fields to support the ratings.

Table 3. Sample Administrative Factors Categories

Category

 Ranking  

Inspection Practices

Medium

Operator Training

High

Management of Change

Low

Maintenance and Repair Practices  

Medium

Written Operating Procedures

High

Operator Surveillance

Medium

Heater and control system designs are evaluated and assigned a ranking similar to the administration factors include the quality of temperature and flow monitoring.  The HSE Consequences of heater failures are evaluated by factors including process pressure and how quickly and safely the heater can be shut down after a failure occurs (See Table 4).  This information, plus the process fluid properties (which is used to assign toxicity, flammability and vapor cloud potential), failure mode and fluid phase are assigned factors used to compute consequence for Mechanical Integrity (MI) failures.  Tube failures that are calculated to result in a release outside of the fire box have much higher HSE consequences than failures that are anticipated to be contained within the heater.  The failure consequences for Non-MI scenarios are arrived at via team discussion and ranking of assigned factors. All values are supported by text-based information documenting the basis that led to the ranking decision.

Table 4. Consequence Critical Factors for MI Failures

 Process Related Factors 

 Equipment Design Factors 

Process Pressure

Failure Mode

Process Fluid Phase

Personnel Proximity

Main Process Fluid Type

Duration of Leak

Failure scenarios are simplified in the work process identifying specific damage mechanisms which affect fired heaters. The metallurgical damage mechanisms and the non-Mechanical Integrity failure modes are listed in Table 5. Each scenario category has a series of critical factors which are used to determine the probability of failure for each scenario for a specific heater. Each critical factor’s ranking (high/medium/low) is selected by the team during the team risk ranking meetings. The software assigns a score for each ranking and a weighted sum of the score is used to compute probability.  Each failure scenario is assigned an Inspection Effectiveness (Metallurgical failure scenarios only) and Personnel Proximity Ranking which is used in the probability of failure calculation.

Table 5. Failure Scenario Categories Used For Heater Risk Ranking Study

 Metallurgical/Mechanical Integrity (MI) Damage Mechanisms 

  Non-MI Failure Scenarios  

Creep

Control Systems

Internal Corrosion

Operator Instructions

Oxidation

 

Environmental Cracking

 

Fatigue

 

Carburization

 

As an example, the critical factors and ranking criteria for creep damage are shown in Table 6. The software assigns a numerical value to each ranking and a weighted sum is computed. The resulting value is combined with inspection effectiveness and personnel proximity ratings to compute the probability category.

Table 6. Sample Critical Factors Evaluation for Creep Rupture

table6

Recommendations

Once probability and consequence are determined for each failure scenario, the heater’s risk ranking is complete. A sample result for a series of heaters is shown in Table 7. The specialist team develops actionable items to address unacceptable risks. As an example, for a heater which has a high identified risk associated with operator procedures, actionable items might include: developing a standard design for observation doors and view ports that allow good view of the coils and tops of flames, define and implement consistent burner and pilot lighting practices, or establish a purge approach that is consistent with industry best practices. For a mechanical integrity risk, such as creep, the actionable items might include perform a creep rupture life remaining life assessment per API 579-1/ASME FFS-1, establish tube metal temperature limits, and/or include inspections to detect creep damage as part of the heater Inspection Test Plan. These actions are targeted at the heaters with the most risk and include a prioritization for short term and long term risk reduction based on Risk Levels, ability to implement during operation, actions requiring a turnaround, and complexity to implement.

Table 7. Sample Risk Rankings Results

 Heater  

Failure Mechanism: Failure Mode

H-106

Creep: Rupture

Control Systems: Operator Injury

Operator Instructions: Operator Injury

Internal Corrosion: Medium Corrosion Hole

Stress Corrosion Cracking: Pinhole/Crack

H-102

Operator Instructions:
Operator Injury

Creep:
Rupture

Control Systems: Operator Injury

Stress Corrosion Cracking: Pinhole/Crack

Internal Corrosion: Medium Corrosion Hole

H-101

Control Systems: Operator Injury

Creep:
Rupture

Operator Instructions: Operator Injury

Internal Corrosion: Medium Corrosion Hole

Stress Corrosion Cracking: Pinhole/Crack

H-105

Creep:
Rupture

Control Systems: Operator Injury

Operator Instructions: Operator Injury

Internal Corrosion: Medium Corrosion Hole

Carburization: Pinhole/Crack

H-070

Creep:
Rupture

Control Systems: Operator Injury

Operator Instructions: Operator Injury

Internal Corrosion: Medium Corrosion Hole

Carburization: Pinhole/Crack

H-060

Operator Instructions: Operator Injury

Control Systems: Operator Injury

Creep:
Rupture

Internal Corrosion: Medium Corrosion Hole

Carburization: Pinhole/Crack

 

Risk Level Key:

High

Medium-High

Medium

Low


Summary

The risk ranking approach described enables sites to identify immediate risks to health, safety and the environment from operation of the heaters and prioritize actions to mitigate the risks. The results from the study identify actionable findings which can be used to prioritize the development and refinement of Preventative Maintenance (PM), Inspection, Operator Surveillance and other actions, such as design changes.

If you have a question relating to this blog, you may post a comment for the authors at the bottom of this page. If you would like to submit an Information Request please click below:

Request Info from Becht

|

About The Author

Contact:
Dr. Eileen Chant has 25 years of experience in the areas of engineering project management, modeling and performance evaluation of mechanical and energy systems. She has managed a number of projects developing and applying risk-based inspection methodologies and software tools for use by the process and power industry in developing cost-effective inspection and maintenance programs in accordance with API RP-580 and the ASME Inspection Planning Document, PCC-3. She has also managed projects developing andapplying fitness-for service software tools in accordance with API 579/FFS-1 and new methodologies for collection, management and statistical analysis of NDE data.